IESCO New Connection Application, Fee & Process

Are you planning to get IESCO New Connection for your home, business, or property? Applying for a new connection with IESCO is an essential step toward accessing reliable electricity. With a streamlined application process and user-friendly services, IESCO ensures you can easily set up your connection while complying with all requirements.

Whether you’re a homeowner or managing a large-scale business, understanding the procedure and documents needed can save you time and effort. Let’s explore everything you need to know to get started with your IESCO New Meter Connection application.

IESCO New meter

Requirements for IESCO New Connection

To apply for a new connection, you need the following documents:

  • Attested copy of CNIC of the applicant
  • Attested copy of witness CNIC
  • Proof of ownership or tenancy, such as property papers or a rental agreement
  • No Objection Certificate (NOC) if applicable
  • Copy of neighbor’s IESCO Bill (for verification)
  • Wiring Test Report (for connections other than domestic)
  • Affidavit stating that no previous connection exists at the premises

How to Apply for IESCO New Connection?

You can apply for a new IESCO connection either online or in person. Here’s how:

Online Application

  1. Visit the IESCO website and navigate to the “Apply New Connection” section.
  2. Fill out the online application form with all required fields.
  3. Upload scanned copies of the required documents.
  4. Submit the application and print a copy for your records.
  5. Attach all required documents to the printed application form.
  6. Send the application and documents to the nearest IESCO office.
  7. After verification, you will receive a Demand Notice.
  8. Pay the Demand Notice at the designated bank and keep a copy of the payment receipt.
  9. Send the payment receipt copy back to IESCO for final processing.

In-Person Application

  1. Obtain five copies of the Application and Agreement (A&A) form from any IESCO office or download it from their website.
  2. Fill in all copies of the A&A form and attach:
    • Proof of ownership
    • Consumer electricity bill from an adjacent premises
    • Wiring test report (if applicable)
    • Affidavit regarding previous connections
  3. Submit all forms and documents at your local IESCO office.

Timeline for Connection

The time taken to establish a new connection varies based on load requirements:

Load RequirementTimeframe (Days)
Up to 15KW30
Above 15KW but not exceeding 70KW53
Above 70KW but not exceeding 500KW73
Above 500KW but not exceeding 5000KW106
For supply at 66KV and above496

By following these steps and ensuring you have all necessary documentation, you can successfully apply for a new electricity connection with IESCO.

IESCO New Meter Connection Charges

Single Phase Service Connection (Rural)

Length of Service LineCharges (Rs.)
Up to and including 40 meters4,000
41-100 meters (with one span of Ant Conductor and one pole)4,000 + Rs. 200 per meter
101-160 meters (with one span of Ant Conductor and two poles)16,000 + Rs. 250 per meter

Single Phase Service Connection (Urban)

Length of Service LineCharges (Rs.)
Up to and including 40 meters4,000
41-100 meters (with one span of Ant Conductor and one pole)4,000 + Rs. 200 per meter
101-160 meters (with one span of Ant Conductor and two poles)16,000 + Rs. 250 per meter

Three Phase Service Connection (Both Urban & Rural)

Length of Service LineCharges (Rs.)
Up to and including 40 meters15,000
41-100 meters (with one span of Ant Conductor and one pole)15,000 + Rs. 260 per meter
101-160 meters (with one span of Ant Conductor and two poles)30,600 + Rs. 300 per meter
160-280 meters (with one span of Ant Conductor and two poles)48,600 + Rs. 340 per meter

IESCO New Connection Track Online

To track your IESCO new connection application online, follow these steps:

  1. Visit the IESCO Application Tracking Page: Go to the official IESCO tracking portal. You can access it directly through IESCO’s tracking page or similar links provided by IESCO.
  2. Select Application Type: Choose “New Connection” from the options available.
  3. Enter Required Information:
    • Tracking ID: If you have received a tracking ID when you submitted your application, enter it here.
    • CNIC: Alternatively, you can enter your CNIC number without dashes.
  4. Submit the Information: After filling in the required fields, click on the submit button to view the status of your application.
  5. Review Application Status: The system will display the current status of your application, including any updates or requirements.

By following these steps, you can easily monitor the progress of your new connection application with IESCO from the comfort of your home.

IESCO Connection Track Online

FAQs of IESCO New Meter Connection

The timeline for obtaining a new connection typically ranges from 30 to 45 days, depending on various factors such as application submission and inspection completion.

Required documents include an attested copy of your CNIC, proof of ownership or tenancy, a No Objection Certificate (if applicable), and a wiring test report.

Yes, IESCO offers an online application portal where you can submit your request for a new connection.

Fees vary based on connection type and length of service line. For example, single-phase connections have specific charges based on the distance from the supply point.

During the site inspection, IESCO officials verify the details provided in your application and ensure that the site meets all technical requirements for installation.

After your application is processed, you will receive a Demand Notice via registered post or can collect it from your local IESCO subdivision office.

Summary

Getting a new electricity connection from the Islamabad Electric Supply Company (IESCO) is essential for homeowners and businesses in the region. The process involves submitting an application along with required documents, undergoing a site inspection, and paying associated fees. IESCO provides both online and in-person application options, making it accessible for all customers. Once the application is approved, a Demand Notice is issued, and upon payment, the connection is installed. Understanding the requirements and process can streamline obtaining reliable electricity service.